Trafficware Ltd    Trafficware Forum    Trafficware Forum  Hop To Forum Categories  SimTraffic™ 7    Varying PHF Time Interval for Different Approaches
Go
New
Find
Notify
Tools
Reply
  
-star Rating Rate It!  Login/Join 
Junior Member
Posted
I have a network that has different peak hour time intervals for different approaches sometimes even within the same intersection. For example, I have an intersection where the peak 15 min volume occurs at 4:15 on the EB leg and the peak 15 minute volume occurs at 4:45 on the SB leg.

In SimTraffic it seems i can only apply the PHF to one time period across the entire network. Thus causing both approaches to peak simultaneously in my simulation which is not correct. Is there a work around for this problem?
 
Posts: 2 | Registered: Tue February 03 2009Reply With QuoteEdit or Delete MessageReport This Post
Member
Picture of John Albeck
Posted Hide Post
Hi BDamiani,

This is true that the PHF adjustment in SimTraffic applies to only one interval. If you wanted a more realistic simulation, then I'd suggest you read the volumes from a UTDF volume data file (Volume.csv format). See page 22-6 of the Synchro Studio User Guide for details on this.

I've attached an example Volume.csv file that can be opened and edited with a spreadsheet. This sample has 3 nodes in it and the INTID must match the node numbers in the Synchro file.

Thanks,

John.


John Albeck
Trafficware


VOLUME-with_ST_UTDF.csv (1 KB, 13 downloads) 15-min Volume CSV file
 
Posts: 1119 | Registered: Fri March 14 2003Reply With QuoteEdit or Delete MessageReport This Post